Aug. 7, 2001: Just dirt. The cul-de-sac from our front yard.
|
|
Oct. 28, 2001: Still just dirt, but with a permit sign.
|
|
Dec. 23, 2001: Finally! Footings. LuAnn is inspecting our current dining
table, backyard trees in the distance.
|
|
Dec. 23, 2001: LuAnn on our front porch, with a similar house (different
colors) in the background.
|
|
Jan. 13, 2002: The foundation is up! (As seen out the window of the
2nd floor of the house being built next door.)
|
|
Jan. 20, 2002: Gravel in the driveway and garage, wood in the front
yard. We didn't expect to see much else, because of all the rain.
|
|
Jan. 26, 2002: Workmen framing the house.
|
|
Jan. 27, 2002: We've been framed!
|
|
Jan. 27, 2002: Inside, upstairs, in the guest bedroom.
|
|
Jan. 27, 2002: Because of the slope of the lot, we have a large
crawlspace in the back.
|
|
Jan. 27, 2002: Graffiti we found on the kitchen window. While everyone
else in NC seems to be celebrating the end of the drought, this sums up our
feelings about the construction delays.
|
|
Feb. 3, 2002: There is a roof, windows, and siding. Finally, a good image
of what our house looks like, although it is an overcast day, so the colors
look a bit lackluster.
|
|
Feb. 3, 2002: Me in the back, under the sliding glass doors. There is a
slope to the lot, so I'll probably be able to almost stand up under the deck.
|
|
Feb. 5, 2002: Our house on a sunny day.
|
|
Feb. 8, 2002: We have a deck! We have wires and plumbing too, but those
pictures aren't as interesting. This picture was taken during the framing
tour.
|
|
Feb. 27, 2002: After 2 weeks of no visible progress, suddenly the
inside of the house is looking very pink.
|
|
Feb. 27, 2002: Meanwhile, the forest behind
our house has gotten considerably thinner and see-thru. (sigh)
That'll be other people's back yards someday.
|
|
Feb. 27, 2002: Our driveway will soon be there.
|
|
Feb. 27, 2002: The current official closing date is March 28.
|
|
Mar. 3, 2002: Our driveway is there.
|
|
Mar. 3, 2002: It's no longer pink inside.
|
|
Mar. 6, 2002: Everything seems to be coming along fine. They are
painting the walls inside.
|
|
Mar. 10, 2002: They've planted trees in our front yard.
|
|
Mar. 10, 2002: Kitchen!
|
|
Mar. 10, 2002: Painted walls, trim, slate on the fireplace, rails on
the stairs, doors in their frames....
|
|
Mar. 14, 2002: The only thing missing from this picture is the carpet.
|
|
Mar. 14, 2002: The only thing missing from this picture is the mirror.
|
|
Mar. 14, 2002: Nothing missing from this picture!
|
|
Mar. 14, 2002: Many things have been added since
Sunday (all the sinks and toilets, light fixtures, outlets, thermostats, much
of the vinyl flooring, etc), but there are still many things to go (doorknobs,
stove, shelving, telephone and cable jacks, etc).
|
|
Mar. 17, 2002: Carpet! Also, mirrors in the bathrooms, shelves in the
closets, and a few other details.
|
|
Mar. 17, 2002: Changes to the outside: a door to the crawlspace,
a trench for utilities, and big green boxes.
|
|
Mar. 20, 2002: Welcome to our home.... (almost).
|
|
Mar. 21, 2002: The closing date has been changed to April 3.
|
|
Mar. 22, 2002: The closing date has been changed to April 5.
|
|
Mar. 24, 2002: A garage door, some cement, and the number
1706.
|
|
Apr. 5, 2002: We closed on the house! We really are moving in this
weekend! Woohoo!
|