




SUGGESTIONS FOR REDUCTION
OF ANALYTICAL COSTS BY
ELIMINATION OF UNNECESSARY
2ND COLUMN CONFIRMATIONS
by Douglas M. Chatham
Senior Chemist
SUMMARY
Many projects have specified that all positive results
for GC methods will be confirmed by second column confirmation
only because the SW846 method provides for it. Many more projects
have suffered from inflated analytical costs because second column
confirmations were not discussed in the work plan or the QAPP
and the laboratory performed these analyses because they were
called for by the SW846 method. The large number of confirmations
resulting from this protocol is excessive and often results in
an unnecessary inflation of the analytical cost. If good historical
data exist, the only analytes requiring confirmation are compounds
not previously detected and confirmed. For example, if benzene
was detected and confirmed by method SW8240 (a GC/MS method) or
by method SW8020 with second column confirmation during Superfund
investigations, a positive result for benzene in the RI/FS investigation
does not need to be confirmed. Positive results less than Quantitation
Limits, MCLs, ARARs, or cleanup levels should not be confirmed.
Sampling efforts involving numerous samples at each site, e.g.
grid sampling, should include only enough confirmations to confirm
the identity of each analyte found at the site. Thorough evaluation
of the need for 2nd column confirmations during planning
stages and frequent communication with laboratory personnel could
reduce analytical costs for GC methods as much as 50%.
RECOMMENDATIONS
If historical data exist, the laboratory should be
directed to conduct second-column confirmations only for compounds
not previously detected. When second-column confirmations are
deemed necessary, the laboratory should confer with the PM or
the QAPO.
Positive results less than Quantitation Limits, MCLs, ARARs, or
cleanup levels should not be confirmed.
Sampling efforts involving numerous samples at each site, e.g.
grid sampling, should have a limited number of confirmations.
DISCUSSION
Second column confirmations apply to organic analyses
using GC methods , such as SW846 methods SW8010, SW8020, SW8021,
SW8080, SW8081 and SW8280. A second column confirmation often
is billed by the laboratory as a separate sample analysis. Method
8000A of SW846 states in Paragraph 7.6.9.1 ";Tentative identification
of an analyte occurs when a peak from a sample extract falls within
the daily retention time window. Normally, confirmation is required:
on a second GC column, by GC/MS if concentration permits, or by
other recognized confirmation techniques. Confirmation may not
be necessary if the composition of the sample matrix is well established
by prior analyses.";(1) Methods SW8010B, SW8011, SW8015A,
SW8020B, SW8021A, and SW8030A, include the statement"; If
analytical interferences are suspected, or for the purpose of
confirmation, analysis using the second GC column is recommended.";
For example, a sampling grid of 100 sampling points with positive
results for benzene, toluene, ethylbenzene, and xylenes (BTEX)
in each sample would result in 200 analyses for BTEX if every
positive result is confirmed. At an analytical cost of $100/sample
for BTEX, the result analytical cost is $20,000. This example
should require no more than five confirming samples which would
be 105 analyses for BTEX and an analytical cost of $10,500. One
investigation submitted 107 samples for an organic GC analysis
costing $176 each. The site had been investigated several times
before, providing adequate historical data to eliminate the need
for 2nd column confirmations. There were 70 2nd column confirmations
resulting in 177 analyses for a total analytical cost of $31,152
(not including other QA/QC samples). These 70 additional analyses
were performed because SW846 method SW8150 provided for them and
they were not specifically addressed by the work plan or the QAPP.
Elimination of the unnecessary 2nd column confirmations would
have saved the project $12,320.
The only confirmations required for initial site
investigations conducted under CLP protocols are GC/MS confirmations
of Pesticide/PCB analyses since the volatiles and semi-volatiles
are analyzed by GC/MS methods. Cost reductions by limitation of
2nd column confirmations could be realized for any sampling investigation
utilizing GC methods.
Types of Investigations
The CERCLA preliminary assessment (PA) and the RCRA
facility assessment (RFA) are used to identify any releases or
migration from a facility based on the existing information and
apparent visual evidence. The PA or RFA are typically the first
step in the CERCLA or RCRA process. Samples are not usually taken
during these assessments.
The CERCLA Site Investigation (SI) and the RCRA Confirmation Sampling
Process (CS) are used to confirm or disprove suspected releases
to an environmental medium based on information obtained during
the PA or RFA. The SI or CS process is generally limited in scope;
the goal is to gather sufficient data to confirm the presence
or absence of contamination at Potential Release Locations (PRLs),
and to provide a basis for the scope of the CERCLA Remedial Investigation
(RI) or the RCRA Facility Investigation (RFI) process or a No
Further Action decision. The data quality levels for SIs or CSs
are generally required to be Level IV (CLP) or Definitive data
(2) since the data is required to be litigation quality. These
investigations are usually the first ones conducted at most sites
and historical data will be limited or non-existent. The only
CLP or Definitive data requiring confirmation analyses are Pesticide/PCB
analyses. If on-site, Level II, or Level III analyses are conducted,
especially with grid sampling, some limitations of 2nd column
confirmations are justified.
The CERCLA Remedial Investigation (RI) and the RCRA Facility Investigation
(RFI) are used to evaluate the nature and extent of the releases
of hazardous waste and hazardous constituents and to gather sufficient
data to support the preparation of a risk assessment and Feasibility
Study (FS) or Corrective Measures Study (CMS). RI/RFI studies
could be screening data with definitive confirmation. These studies
are much more extensive than SI/CS investigations. The screening
data could be on-site and/or Level II fixed laboratory analyses
with 10% Level III or CLP definitive confirmations. Limitations
on second column confirmations could be based on historical data
and grid sampling limitations as discussed above.
The CERCLA Feasibility Study (FS) and the RCRA Corrective Measures
Study (CMS) are used to develop and evaluate a remediation plan
or corrective measures alternatives and to recommend the appropriate
corrective measure for the facility. FS/CMS studies could be screening
data with definitive confirmation. These studies can be as extensive
as RI/RFI investigations, but FS/CMS studies are much more focused.
The analyses are limited to the analytes of concern which have
been well documented in prior investigations. The screening data
could be on-site and/or Level II fixed laboratory analyses with
10% Level III or CLP definitive confirmations. Limitations on
second column confirmations could be based on historical data
and grid sampling limitations as discussed above. It is likely
that second column confirmations would not be needed for these
studies.
The CERCLA Remedial Design/Remedial Action (RD/RA) and the RCRA
Corrective Measures Implementation (CMI) are used to design, construct,
operate, maintain, and monitor the performance of the remedial
action or corrective measure selected. These studies can be as
extensive and focused as FS/CMS investigations. The analyses are
limited to the analytes of concern which have been well documented
in prior investigations. The screening data could be on-site and/or
Level II fixed laboratory analyses with 10% Level III or CLP definitive
confirmations. Second column confirmations are not needed for
these studies.
The basic purpose of cleanup verifications and long-term monitoring
is to demonstrate that the concentrations of contaminants are
below a mandated level. Second column confirmations are not needed
for these studies.
LIST OF REFERENCES
1. EPA, Test Methods for Evaluating Solid Waste,
Physical/Chemical Methods, SW-846, 3rd Edition, Final Update 1,
November 1990.
2. EPA, Data Quality Objectives Process for Superfund, Interim
Final Guidance, p. 42, EPA540-R-93-071, September 1993.
Submit your page to 34 popular sites for free, using one form!